Scaling 3 or 4 Pumped Storage Hydro Schemes for equal duration regeneration

Scaling 3 or 4 pumped hydro schemes for equal duration regeneration

Suppose there are 3 planned Pumped Storage Hydro (PSH) schemes of different energy storage capacities – for example, SSE Coire Glas @ 30GWh, ILI Balliemeanoch 45GWh and Glasa Morie Glass 170GWh – and we want to scale the installed power regeneration turbines so that they can all operate with an equal duration of regeneration in a co-ordinated manner to offer the National Grid,  OFGEM, BEIS or whatever other customer the opportunity to place an order for a desired total power capacity for a desired duration of regeneration.

If the customer requirements for total energy storage capacity (equal to total power multiplied by duration) exceed the sum of the energy storage capacities of the 3 planned PSH schemes – in this example, 245GWh – then we may need to specify the requirements of a 4th PSH scheme’s energy storage and power regeneration capacity in order to plan to satisfy the customer’s order.

The graph plots a x=power / y=duration curve for each of the 3 specified PSH schemes – Coire Glas 30GWh (green curve), Balliemeanoch 45GWh (black curve) and Glasa Morie Glass 170GWh (red curve).

The graph plots 3 alternative desired total power capacities – 8.17GW, 12.25GW and 20GW (the orange lines) and the x-value on these total power lines represents the required power of a 4th PSH scheme and when x=0 then a 4th PSH scheme is not required.

The equation relating the power of the 4th PSH scheme (P4x) to the total power (TP) of all 3 or 4 PSH schemes with duration y is –

P4x = TP – 30÷y – 45÷y – 170÷y

The graph plots 3 alternative desired durations – 12.25 hours, 20 hours and 30 hours (points with the same y value, reading horizontally, as tabulated below).

Scaling 3 or 4 Pumped Storage Hydro Schemes for equal duration
Duration
(Hours)
Total Power
(GW)
30GWh Coire Glas Power(GW)  45GWh Balliemeanoch
Power (GW)
170GWh Glasa Morie Glass
Power(GW)
4th PSH Scheme
Power(GW)/
Energy(GWh)
30Hours 8.17GW 1GW 1.5GW (ILI) 5.67GW 0
30Hours 12.25GW 1GW 1.5GW (ILI) 5.67GW 4.08GW
122.5GWh
30Hours 20GW 1GW 1.5GW (ILI) 5.67GW 11.83GW
355GWh
20Hours 12.25GW 1.5GW (SSE) 2.25GW 8.5GW 0
20Hours 20GW 1.5GW (SSE) 2.25GW 8.5GW 7.75GW
155GWh
12.25Hours 20GW 2.45GW 3.67GW 13.88GW 0

The Coire Glas site is suitable to build a PSH scheme at a much greater scale and so, as an alternative to planning for a 4th PSH scheme, Coire Glas could be supersized as follows.

Scaling 3 Pumped Storage Hydro Schemes for equal duration
Duration
(Hours)
Total Power
(GW)
 45GWh Balliemeanoch
Power (GW)
170GWh Glasa Morie Glass
Power(GW)
Coire Glas
Power(GW)/
Energy(GWh)
30Hours 8.17GW 1.5GW (ILI) 5.67GW 1GW
30GWh
30Hours 12.25GW 1.5GW (ILI) 5.67GW 5.08GW
152.5GWh
30Hours 20GW 1.5GW (ILI) 5.67GW 12.83GW
385GWh
20Hours 12.25GW 2.25GW 8.5GW 1.5GW
30GWh (SSE)
20Hours 20GW 2.25GW 8.5GW 9.25GW
185GWh
12.25Hours 20GW 3.67GW 13.88GW 2.45GW
30GWh

 